Sovereign Metals steps on the accelerator at Kasiya graphite development

November 24, 2023

Sovereign Metals (ASX: SVM) has stepped up key activities at its world-class Kasiya project in Malawi as it prepares to demonstrate the commercial viability of its graphite product to the world.


Backed by strategic development partner Rio Tinto (ASX: RIO) and a highly supportive local government, Sovereign is fast-tracking a number of aspects in its plan to supply a rapidly-growing lithium-ion battery market with high-grade graphite.


Sovereign has recently commenced a bulk sampling program that will extract over 100 tonnes of ore from Kasiya.


The graphite produced from the bulk sampling program will then be shared with prospective end-users in addition to being used for upscaled downstream test-work.



This is an important component of an initiative that will allow the company to proceed to customer qualification, downstream testwork and product development.


Major graphite market developments

Rio Tinto’s recent decision to invest $40.4 million into Kasiya is a significant acknowledgement that Kasiya is considered one of the world’s largest natural graphite deposits outside of China with the potential to become a key source of strategic supply to the US, UK, EU, Japan and South Korea.


That was further confirmed with a recently released pre-feasibility study (PFS) identified Kasiya as a major critical minerals opportunity which has the potential to deliver significant long-term volumes of natural rutile and graphite.


The PFS forecast that Kasiya is capable of achieving one of the lowest cash operating costs globally at $630 per tonne and the lowest CO2-footprint.


Sovereign’s managing director Frank Eager said the acceleration of activities in the Kasiya program comes as China, which currently produces 61% of all flake graphite used in the production of lithium-ion battery anodes and accounts for 93% of all graphite anode production globally, implements curbs on exports of natural graphite under “national security” concerns.


This is expected to lead to a global shortfall in product supply and a potential uptick in graphite prices.


Bulk sampling activities

As part of the acceleration of activities at Kasiya, Sovereign and Rio Tinto have agreed to collaborate to qualify graphite from the project with a particular focus on supplying the spherical purified graphite (SPG) segment of the lithium-ion battery anode market.


Sovereign has acquired a custom-made 300mm diameter spiral auger to extract over 100 tonnes of material from across Kasiya’s planned future pits with sampling to a maximum 20m depth as part of the mechanised drill program for the bulk sampling activities.


The 1000 kilogram bulk sample will then be processed at the company’s laboratory in Lilongwe, Malawi.


High-grade results tipped

The graphite pre-concentrate is expected to grade at between 4 to 5% carbon total whilst the heavy mineral concentrate is expected to grade ~30% contained rutile.


The sample will then be shipped to Australia for final processing at commercial metallurgical laboratories in Canada.


The graphite pre-concentrate will undergo traditional flotation and polishing processes to target >96% carbon total product for lithium-ion battery anode feedstock.


The heavy mineral concentrate will undergo gravity spiral cleaner stages followed by electrostatic and magnetic separation stages to produce a +95% TiO2 natural rutile product.


Recent initial graphite characterisation testwork conducted by an independent German industrial minerals specialist demonstrated superior qualities and excellent suitability for its use in lithium-ion batteries.


Further downstream testwork is planned that will use the graphite concentrate produced from this current bulk sampling program.





Source: https://smallcaps.com.au/sovereign-metals-steps-on-accelerator-kasiya-graphite-development/

July 9, 2024
The Queensland Government has broken ground on the first construction works of the $5 billion CopperString project. Work commenced yesterday on the CopperString projects’ first and largest workforce accommodation site. The site will house those charged with building the project’s 840km high-voltage transmission line that will connect Mount Isa to the ‘SuperGrid’ for the first time. The workforce accommodation will house up to 550 construction workers at its peak. These workers will construct a nearby substation and progress early stages of the transmission line development heading west from Hughenden out to Mount Isa. Supercharging the state’s north-west aims to unlock Queensland’s $500 billion north-west minerals province. It’s expected CopperString will be complete in 2029, weather and construction conditions permitting. Queensland Premier Stephen Miles said CopperString is the biggest ever expansion to the state’s publicly owned energy system. “Queenslanders deserve cheaper, cleaner, more reliable energy – to power their homes, our schools, hospitals, shopping centres and more,” Miles said . “CopperString will be the catalyst for transforming Queensland’s north and north-west – opening up mining opportunities, creating more jobs and unlocking critical minerals which will be essential in developing renewable technologies. “This is the start of a long and exciting future for the region and our state.” Commencing later this month, project owner, Queensland Powerlink, will be offering free sessions for businesses along the CopperString corridor to build their capabilities. The program includes five workshops and one-on-one assistance to help businesses build confidence to bid on major projects and supply chain work in the region. “All of North Queensland understands the immense opportunities that CopperString presents for local jobs both directly and indirectly which is why this is such a momentous day,” Resources and Critical Minerals Minister Scott Stewart said.  “Critical minerals are the next big boom for the resources industry and the feedback I’ve had from companies is that this project is key to unlocking those opportunities.” Source: https://www.australianmining.com.au/queensland-breaks-ground-on-copperstring/
July 8, 2024
Underground mines are busy places, and it’s vital companies are on top of their processes to enable an efficient and safe underground operation. Whether it’s having the best equipment to drive higher production, maximise return on investment, minimise waste or keep workers out of harm’s way, mining companies benefit from understanding and investing in the right underground technologies. Source: https://www.australianmining.com.au/showcasing-the-best-in-underground-mining/
July 8, 2024
BHP has started environmental processing to have the transport at its Escondida copper mine in Chile transitioned to an electric trolley system. The Big Australian will invest around $US250 million ($371.6 million) in the project at Escondida, which it owns in a joint venture with Rio Tinto. The funds will go towards installing key infrastructure to electrically assist the movement of extraction trucks in areas where the highest fuel consumption currently takes place. BHP has submitted an environmental impact statement to the Environmental Impact Assessment System in Chile. “The electric trolley system is one of the initiatives with which we seek to move towards a safer and more sustainable way of operating hand in hand with technology,” BHP Escondida president Alejandro Tapia said . “This project will allow us to reduce the fuel consumption of our extraction trucks and thus advance our goal of net-zero operational greenhouse gas emissions by 2050.” The project includes the construction of a new electrical substation and transmission lines both inside and around the Escondida Norte pit. These facilities will electrically assist the movement of trucks inside the mine in the areas where they go up loaded with ore and, consequently, consume more fuel. With this new technology, instead of using diesel, they will be propelled by electrical power, reducing greenhouse gas emissions and improving productivity associated with truck performance given the higher travel speed. Once construction kicks off up to 160 jobs are expected to be created. The trolley project is in addition to other technological transformation initiatives that the company maintains in different stages of study and execution, including the progressive incorporation of autonomy in its mining equipment.  To date, Escondida has six autonomous trucks in full operation and by 2025 it expects to have the largest fleet of autonomous equipment in South America. Source: https://www.australianmining.com.au/bhp-goes-green-at-worlds-largest-copper-mine/
Share by: