Blog Layout

Great Fingall development has begun

November 7, 2023

Westgold Resources has commenced decline development of its Great Fingall gold mine in Western Australia.


Located 28km from Westgold’s Tuckabianna processing hub, Great Fingall has produced approximately 1.2 million ounces over the years, with decline development to extend the mine’s life.


With the Westgold board approving Great Fingall’s development in August, the company has now mobilised the key underground fleet, supporting surface infrastructure and high-speed development team to commence development in less than two months.


The Great Fingall development team completed the first cut into the existing decline access on October 19, which was in line with the Great Fingall feasibility study.


As per the feasibility study, the mine is expected to produce more than 45,000 ounces per annum across eight years. The ore processed at the Tuckabianna mill is at an all-in cost of $1801/oz.


“Great Fingall is one of four +1Moz (more than one million ounces) historic producing mines in Westgold’s portfolio,” Westgold Resources managing director Wayne Bramwell said. “At steady state, Great Fingall will be a long-life, high-grade, high-margin underground mine, producing +45,000oz a year.


“Our base case plan boasts compelling returns, is fully funded from operational cashflows and focuses on deeper virgin reef extensions only. Importantly, significant upside exists from known shallow high-grade, flat and linking structures that we will develop through as we push the decline past the shallow remnant mining areas to the virgin extensions of this high-grade orebody.


“These opportunities, which could deliver additional ounces during FY24 (2024 financial year), have not yet been included in the current business case or design.”


Great Fingall’s first ore is anticipated in the first half of 2025.




Source: https://www.australianmining.com.au/great-fingall-development-has-begun/

July 9, 2024
The Queensland Government has broken ground on the first construction works of the $5 billion CopperString project. Work commenced yesterday on the CopperString projects’ first and largest workforce accommodation site. The site will house those charged with building the project’s 840km high-voltage transmission line that will connect Mount Isa to the ‘SuperGrid’ for the first time. The workforce accommodation will house up to 550 construction workers at its peak. These workers will construct a nearby substation and progress early stages of the transmission line development heading west from Hughenden out to Mount Isa. Supercharging the state’s north-west aims to unlock Queensland’s $500 billion north-west minerals province. It’s expected CopperString will be complete in 2029, weather and construction conditions permitting. Queensland Premier Stephen Miles said CopperString is the biggest ever expansion to the state’s publicly owned energy system. “Queenslanders deserve cheaper, cleaner, more reliable energy – to power their homes, our schools, hospitals, shopping centres and more,” Miles said . “CopperString will be the catalyst for transforming Queensland’s north and north-west – opening up mining opportunities, creating more jobs and unlocking critical minerals which will be essential in developing renewable technologies. “This is the start of a long and exciting future for the region and our state.” Commencing later this month, project owner, Queensland Powerlink, will be offering free sessions for businesses along the CopperString corridor to build their capabilities. The program includes five workshops and one-on-one assistance to help businesses build confidence to bid on major projects and supply chain work in the region. “All of North Queensland understands the immense opportunities that CopperString presents for local jobs both directly and indirectly which is why this is such a momentous day,” Resources and Critical Minerals Minister Scott Stewart said.  “Critical minerals are the next big boom for the resources industry and the feedback I’ve had from companies is that this project is key to unlocking those opportunities.” Source: https://www.australianmining.com.au/queensland-breaks-ground-on-copperstring/
July 8, 2024
Underground mines are busy places, and it’s vital companies are on top of their processes to enable an efficient and safe underground operation. Whether it’s having the best equipment to drive higher production, maximise return on investment, minimise waste or keep workers out of harm’s way, mining companies benefit from understanding and investing in the right underground technologies. Source: https://www.australianmining.com.au/showcasing-the-best-in-underground-mining/
July 8, 2024
BHP has started environmental processing to have the transport at its Escondida copper mine in Chile transitioned to an electric trolley system. The Big Australian will invest around $US250 million ($371.6 million) in the project at Escondida, which it owns in a joint venture with Rio Tinto. The funds will go towards installing key infrastructure to electrically assist the movement of extraction trucks in areas where the highest fuel consumption currently takes place. BHP has submitted an environmental impact statement to the Environmental Impact Assessment System in Chile. “The electric trolley system is one of the initiatives with which we seek to move towards a safer and more sustainable way of operating hand in hand with technology,” BHP Escondida president Alejandro Tapia said . “This project will allow us to reduce the fuel consumption of our extraction trucks and thus advance our goal of net-zero operational greenhouse gas emissions by 2050.” The project includes the construction of a new electrical substation and transmission lines both inside and around the Escondida Norte pit. These facilities will electrically assist the movement of trucks inside the mine in the areas where they go up loaded with ore and, consequently, consume more fuel. With this new technology, instead of using diesel, they will be propelled by electrical power, reducing greenhouse gas emissions and improving productivity associated with truck performance given the higher travel speed. Once construction kicks off up to 160 jobs are expected to be created. The trolley project is in addition to other technological transformation initiatives that the company maintains in different stages of study and execution, including the progressive incorporation of autonomy in its mining equipment.  To date, Escondida has six autonomous trucks in full operation and by 2025 it expects to have the largest fleet of autonomous equipment in South America. Source: https://www.australianmining.com.au/bhp-goes-green-at-worlds-largest-copper-mine/