Monadelphus sues for $33m over cost of pipeline delay

Sunday 20th of March 2016 01:57:50 PM



Mondadelphus has taken legal action against developers of a Fortescue Metals Group gas pipeline for at least $33 million over cost blowouts.

The engineering giant is claiming that the Pilbara pipeline was completed 3 months late due to disruptions and delays from clients.

It had a $96 million contract with DPB Development Group (DDG) and TEC Pilbara.

Monadelphus are seeking $19 million from DDG and a further $14 million from TEC as well as interest and costs.

The claim is alleging higher costs were incurred because of a late start, which upset construction plans and pushed the project into Pilbara’s disruptive summer wet season and contract variations requested by DDG.

The writ filed last week says Monadelphous’ practical completion of the pipeline was achieved in March 2015 instead of December 2014 as agreed.

It accuses DDG of not providing adequate access to the site until November 2014, several months later than required under the contract.

One of the reasons cited for the delays was construction consent from the State Government being obtained 24 days later than scheduled.

A Monadelphus joint venture is currently disputing a $200 million blowout in Gladstone’s Wiggins Island coal export terminal.



Full Story

Recent Related News

Monadelphous Awarded $55M in Contracts

Thursday 20th of July 2017 08:00:31 AM

Monadelphous Group Limited announced on Wednesday it has been awarded a number of new work packages with a combined value of approximately $55 million. The engineering company will carry out piping modification and fabrication for Technip Oceania Pty Ltd (TechnipFMC) on the hook-up and ....


Monadelphous secures $170m contract

Friday 30th of June 2017 09:04:25 AM

Monadelphous Group Limited announced this week it has secured new construction and fabrication contracts worth approximately $170 million. The engineering company has secured a new contract with JKC Australia LNG to carry out works at the Ichthys Project Onshore LNG Facilities in Darwin. The ....


Monadelphus sues for $33m over cost of pipeline delay

Sunday 20th of March 2016 01:57:50 PM

Mondadelphus has taken legal action against developers of a Fortescue Metals Group gas pipeline for at least $33 million over cost blowouts. The engineering giant is claiming that the Pilbara pipeline was completed 3 months late due to disruptions and delays from clients. It had a $96 million ....


Monadelphous announces two year contract

Monday 11th of January 2016 09:31:44 AM

Engineering company Monadelphous Group has has announced MGJV has secured a new two year contract for services on the Karratha Gas Plant Life Extension Program, in Western Australia’s Pilbara region. MGJV is a 70:30 joint venture between Monadelphous Group Limited and Giovenco Industries ....


New contracts for Monadelphous

Tuesday 3rd of November 2015 08:42:25 AM

Monadelphous Group has been awarded new contracts in the resource and energy sector worth about $150 million. The Perth based engineering company announced on Monday it has won a contract with Nyrstar Port Pirie Pty Ltd. Monadelphous will perform installation of structural, mechanical and ....


Y Fronts teaser bannerDowner Group MiningLink prefered resume writers Civil Link Banner
Diesel Or Mechanical Fitters With Cat Experience Permanent Roles
Diesel Fitters & Mechanical Fitters with working experience on CAT equipment i.e. D10 & D11 Dozers, 793F & 797 Trucks among other gear required.

Mobilisation Logistics Coordinator
We are seeking a Mobilisations Logistics Coordinator to assist in the coordination of manning and resources for mining shutdown maintenance.

Trade Qualified Electricians Needed
Electrician's required to work on Heavy Mining Equipment. You will be working with a well sought after company located in the Moss Vale, NSW.

Looking For A Change Diesel Fitters With Cat Exp Permanent Workshop Roles
Diesel Fitters & Mechanical Fitters with working experience on CAT equipment i.e. D10 & D11 Dozers, 793F & 797 Trucks among other gear required.

Labourer / Bus Driver
Large Scale Oil & Gas Project • Darwin residential ONLY • Diverse and dynamic environment

Prelude Arrives In Australia
Shell Australia's Prelude floating liquefied natural gas (FLNG) facility has arrived in Australian waters this week after its 5,800km journey from the Samsung Heavy Industries shipyard in Geoje, ....

Australia's Largest Testing Rig Unveiled In Rocky
Siemens has invested $5 million into the Rockhampton Service Centre, which unveiled this week, Australia’s largest and most advanced gearbox load test rig for mining, wind power and other core ....

Dinosaur Find At Qld Mine Site
Palaeontologists and volunteers will work over the next month excavating and studying 30,000-year-old dinosaur bones at the South Walker Creek mine in Central Queensland. The team of eight people, ....

Black Thoated Finch Puts New Coal Mine At Risk
The controversial black throated finch is back to cause problems for Adani with a fresh legal challenge over the planned Carmichael coalmine. New advice has found the federal environment ....

Monadelphous Awarded $55M In Contracts
Monadelphous Group Limited announced on Wednesday it has been awarded a number of new work packages with a combined value of approximately $55 million. The engineering company will carry out ....